Project Profile:

The Guangpu Dagou Emergency Sewage Treatment Demonstration Project in Guandu District of Kunming City is located in Guangpu Dagou, Puzi Village, Guandu District. The treatment object is urban inland river water. The project was constructed by Beijing Luheng Science and Technology Co., Ltd. in August 2018. The treatment scale is 5000 m/d. The system includes water intake device, main treatment process device, dosing and sludge treatment device, and supporting projects. The raw water is elevated to a highly efficient non-power sewage purification device by setting an integrated intake pump station with mechanical fence in the river, and the sewage is discharged up to the standard after treatment.

Project introduction

Engineering survey


      The Guangpu Dagou Emergency Sewage Treatment Demonstration Project in Guandu District of Kunming City is located in Guangpu Dagou, Puzi Village, Guandu District. The treatment object is urban inland river water. The project was constructed by Beijing Luheng Science and Technology Co., Ltd. in August 2018. The treatment scale is 5000 m/d. The system includes water intake device, main treatment process device, dosing and sludge treatment device, and supporting projects. The raw water is elevated to a highly efficient non-power sewage purification device by setting an integrated intake pump station with mechanical fence in the river, and the sewage is discharged up to the standard after treatment.



Leadership concern


      On the morning of September 30, 2018, the Secretary of Guandu District Committee and Lichuan led a team to investigate the renovation of Guangpu Dagou Emergency Sewage Treatment Demonstration Project.
The investigation team listened to the reports of the relevant street and district water bureaus and district residential construction bureaus, and studied and determined the relevant work matters. The Secretary of the District Committee and Lichuan acknowledged the progress of the project and instructed that the demonstration project of emergency sewage treatment should be turned into a top-quality project.


Secretary of Guandu District Committee and on-site guidance of Lichuan Project



Water quality comparison before and after treatment


Pre-treatment river condition

Water quality comparison before and after treatment

Sweeping Pays Attention to Us
Welcome to inquire 010-57780008
  • ABOUT US
  • NEWS CENTER
  • Technology and Application
  • ENGINEERING CASE
  • JOIN GREEN
Copyright Beijing Green Heng Technology Co., Ltd Website Record No:Beijing ICP No. 14042383